LOW VOLTAGE CIRCUIT BREAKER TESTING BASIC INFORMATION AND TUTORIALS

What test to conduct for low voltage circuit breaker?

Low-voltage circuit breakers come in the following three major types:
a) Power (air-frame) circuit breakers;
b) Molded-case circuit breakers;
c) Insulated-case circuit breakers.

Power circuit breakers start with a frame size of 600 A and go up to 4000 A. The sensing unit that operates the breaker on a short circuit or overload may be either an oil-dash pot with springs and copper coils (for older breakers) or may consist of current transformers (CT) and an electronic trip unit.

With the advent of the electronic trip unit, the number of possible settings and trip functions has dramatically increased, making it easier to coordinate circuit breakers with other protective devices.

Molded-case circuit breakers and insulated-case circuit breakers are very similar in mechanical construction and insulation. The circuit breakers' contacts and operating mechanisms are totally enclosed in a molded plastic housing.

The difference between the two is that a molded-case circuit breaker normally has a thermal-magnetic trip unit (i.e., a trip unit made up of two pieces: a thermal unit to sense overload that uses two dissimilar metals and a magnetic unit to trip on short circuit), while an insulated-case circuit breaker has CTs and an electronic trip unit built into the insulated case.

The most thorough test for all three types of circuit breakers is by "primary injection". A special test set that puts out high (fault level) current at low voltage (typically 6-20 V ac) is used to functionally test the circuit breaker.

These test sets have built-in timing functions; therefore, the breaker can be tested at various currents in order to make sure that it operates within the time-current specifications that are provided by the manufacturer and that it is calibrated to perform in conformance with the coordination study.

For circuit breakers that have electronic trip units, it is often possible to do "secondary injection" testing. This is usually done with a special test set that is designed for the trip unit.

It injects low-level test currents into the trip unit, directly testing only the trip unit. For this reason, primary injection testing is a better practice, as it tests the whole circuit breaker (CTs, shunt trip, etc.) in a manner that is similar to how the breaker would operate during a fault.

In addition to testing the tripping characteristics of the circuit breaker by injecting current, it is also normal practice to test the insulation resistance (usually at 1000 V dc) and the resistance of the breaker's contacts. The contact resistance can be measured directly with a low resistance ohmmeter (usually in milliohms) or indirectly by performing a millivolt drop test.

A millivolt drop test is performed by using a primary injection test set to inject rated continuous current through the breaker while measuring the millivolt drop across the breaker's poles. It is a comparative test between each phase of the breaker in which the millivolt reading typically should not differ by more than 50% between phases.

Power circuit breakers have mechanical adjustments and inspections that should also be periodically checked. The manufacturer's instructions list the adjustments for each model.

PROTECTIVE RELAY TESTING BASIC INFORMATION AND TUTORIALS

What is protective relay testing? How to do protective relay testing?

Protective relaying is a very broad subject. Only a brief overview can be given here. There are two major objectives in protective relaying.

First, a protective relay serves to provide equipment protection (i.e., locate and isolate overloads, short circuits, undervoltages, and other types of electrical problems quickly in order to minimize damage).

Second, the protective device that is closest to the problem should operate first to clear the problem, and no other device should operate unless the closest one fails. This concept, known as "selective tripping" or "selectivity", maintains service to as much of the electrical system as possible by isolating only the problem area.

In order to achieve these objectives, each relay must function as it was designed, and the relays must function in conjunction with the other protective devices in the system. Having all the protective devices function as one overall protective system is called "coordination".

Each protective device has specific parameters within which it has been designed to operate. For example, a single element fuse has a value of current above which it opens.

It takes a specific amount of time for a given current to melt the link away and open the fuse. Manufacturers of fuses publish "time-current" curves that show how long it takes a fuse to operate for varying current values.

Generally, the higher the current, the shorter the time.

This same inverse current-vs.-time concept is used for overcurrent relays and for low-voltage circuit breakers. Relays and low-voltage circuit breakers (with internal trip units) have a range of "pickup" operating current that causes them to operate.

In many cases, this value of current is adjustable. By properly selecting the type, characteristic, and/or setting of fuses, relays, or circuit breakers, the system can be coordinated so that the device that is closest to the problem opens before any device upstream of it. It is necessary to select compatible time current characteristics of the devices for the entire system, in addition to selecting the proper settings for the devices.

Prior to performing protective relay testing, a coordination study should be completed to determine the proper settings for the relays to be calibrated. This is usually done by the design engineer when the system is first installed. If there have been revisions or additions to the system, a new study may be necessary.

Once the coordination study has been completed, the relays need to be calibrated to the proper settings. There are special test sets available for this purpose that inject currents and voltages, as necessary, and time the various operations of the relays.

This type of testing is usually performed by a technician who specializes in this area. Depending upon the relay to be calibrated, quite complex test equipment may be required and in-depth training in protective relaying may be needed to properly set the relay.

MEDIUM AND HIGH VOLTAGE CABLE TESTING BASIC INFORMATION AND TUTORIALS

Most cables that are rated for use at voltage levels above 600 V are shielded cables. A shielded cable has a conductor in the center, a semiconducting layer over the strands that is surrounded by insulation, a semiconducting layer, and then a metal foil or wire mesh that surrounds the whole assembly.

There is usually another layer over the shield that makes up the outer jacket of the cable. It is a common practice to hi-pot test the cables on initial installation in order to verify that the cables were not damaged when they were pulled into place and that all the splices and/or terminations were installed properly.

The voltage level that is selected usually is lower than factory test levels, frequently 80% of the dc equivalent of the factory test level.

There are normally two considerations that are given to hi-pot testing of cables as a routine maintenance practice. One is a function of the chosen maintenance philosophy [i.e., breakdown maintenance, preventive maintenance, predictive maintenance, or reliability-centered maintenance (RCM)].

The other depends upon the type of operation and how critical it is to have continuous power without interruption.

The debate on whether or not to perform maintenance hi-pot testing centers around the fact that a cable in marginal condition can be caused to fail by the hi-pot test itself. A cable that is in good condition should not be harmed.

People who subscribe to maintenance testing feel that it is much better to have the cable fail under test. Cable maintenance testing frequently is performed at 50-65% of the factory test voltage.

Problems can then be corrected while the circuit is intentionally shut down, thus avoiding an in-service failure that could interrupt production.

It is important to remember that the necessary material, such as splice kits or cable terminations, should be available to facilitate repairs should the cable fail during testing.

HIGH POTENTIAL (HI POT) TESTING BASIC INFORMATION AND TUTORIALS

What is HiPot testing?

High-potential testing, as its name implies, utilizes higher levels of voltage in performing the tests. It is generally utilized on medium-voltage (1000Ð69 000 V) and on high-voltage (above 69 000 V) equipment.

As stated earlier, the leakage current is usually measured. In some cases, such as in cable hi-potting, the value of leakage current is significant and can be used analytically. In other applications, such as switchgear hi-potting, it is a pass/fail type of test, in which sustaining the voltage level for the appropriate time (usually 1 min) is considered "passing."


INSULATION RESISTANCE TEST BASIC INFORMATION AND TUTORIALS

What is insulation resistance test? How to conduct insulation resistance test?

Insulation resistance tests are typically performed on motors, circuit breakers, transformers, low-voltage (unshielded) cables, switchboards, and panel boards to determine if degradation due to aging, environmental, or other factors has affected the integrity of the insulation.

This test is normally conducted for 1 min, and the insulation resistance value is then recorded. As mentioned earlier, the electrical properties of the insulation and the amount of surface area directly affect the capacitance between the conductor and ground, and therefore affect the charging time.

With larger motors, generators, and transformers, a common test is to measure the "dielectric absorption ratio" or the "polarization index" of the piece of equipment being tested. The dielectric absorption ratio is the 1 min insulation resistance reading divided by the 30 s insulation resistance reading.

The polarization index is the 10 min (continuous) insulation resistance reading divided by the 1 min reading. Both of these provide additional information as to the quality of the insulation.

Many types of insulation become dry and brittle as they age, thereby becoming less effective capacitors. Thus, a low polarization index (less than 2.0) may indicate poor insulation.

Even though insulation may have a high insulation resistance reading, there could still be a problem, since the motor and transformer windings are subjected to strong mechanical stresses on starting. With the exception of electronic equipment (which can be damaged by testing), insulation resistance testing is normally done on most types of new equipment and is also part of a maintenance program.

It is a good practice to perform insulation resistance testing on switchgear and panelboards after maintenance has been performed on them, just prior to re-energizing them. This prevents re-energizing the equipment with safety grounds still applied or with tools accidentally left inside.